2 Replies to “TEM maintenance completed (1/4-7/2011, 1/12-14/2011)”

  1. A refurbished goniometer replaced the old one. New apertures were installed. TEM relaigned. TEM has been working well since last Friday. Job done. Please let me know if there is any further issue.

  2. The maintenance was completed by 1/7/2011. Some minor problems were solved. Because some parts of the current goniometer were worn away, service engineer is trying to get a better one for us. If the parts arrives soon, there may be further maintenance from 1/13 to 1/14. Please check reservation calendar